• December 18, 1987

Severin Sea Lodge

Severin Sea Lodge

800 600 Triad Architects

Triad were commissioned by Severin Sea Lodge to carry out full refurbishment of one hundred rooms and construct new kitchens and conference facility in the centre of the hotel. This involved critical project management as the hotel was still in operation during refurbishment. An extremely tight budget was set.

Triad worked closely with the hotel project team to develop designs, select materials and control the construction process. A tight programme was essential to meet the tourist high season and Triad allocated staff to the site to ensure the contractor was not held up for lack of information and so that design decisions could be made quickly on site.

Project targets were achieved, cost targets were met and the hotel opened on time.

Client: Severin Group
Project Location: Mombasa, Kenya
Gross Area:9000sq. metres
Completion : 1987
Project Partner: Tim Vaulkhard
Project Architect: Shan Khan